NEW QUESTION # 12
Which of the following states appear in the process flow indicator at the top of the Demand form by default?
(Choose three.)

  • A. Draft
  • B. Screening
  • C. Deferred
  • D. Updated
  • E. Approved

Answer: A,B,E


NEW QUESTION # 13
Which plugin activates the ideas module to gather and evaluate ideas efficiently, and quickly identify ideas for implementation?

  • A. Agile Development 2.0
  • B. Ideation with PPM
  • C. Resource Management
  • D. Test Management 2.0

Answer: C


NEW QUESTION # 14
Which role can configure the parameters of the demand workbench that is provided with the base system?

  • A. it_pps_admin.
  • B. it_project_manager
  • C. All roles.
  • D. business_stakeholder.

Answer: A


NEW QUESTION # 15
What is the demand workbench used for? (Choose two.)

  • A. Displaying submitted demands to stakeholders.
  • B. Approving demands.
  • C. Comparing demands with portfolios.
  • D. Comparing and prioritizing demands against other demands.

Answer: A,D


NEW QUESTION # 16
The information displayed on Project Workspace is setup in which table?

  • A. vtb_card_history
  • B. pm_home_page_card
  • C. pm_project
  • D. vtb_card

Answer: B


NEW QUESTION # 17
What system role is needed to manage programs?

  • A. it_project_manager
  • B. it_portfolio_manager_admin
  • C. it_program_manager
  • D. it_program_manager_admin

Answer: C


NEW QUESTION # 18
In which table can you find cost information for a specific fiscal period?

  • A. cost_plan_breakdown
  • B. pm_project
  • C. cost_plan
  • D. expense_line

Answer: A


NEW QUESTION # 19
When a time card is approved, the actual time is stored in which two tables? (Choose two.)

  • A. Resource Event table
  • B. Resource Allocation Daily table
  • C. Resource Aggregate tables (Daily, Weekly, and Monthly)
  • D. Project Time table

Answer: B,C


NEW QUESTION # 20
A customer requires five (5) teamspaces to support different departments. What should you do?

  • A. Contact the Account Representative to activate the teamspaces.
  • B. Use UI Policies and Business Rules to enable teamspaces.
  • C. Enable the teamspace property.
  • D. Activate via each teamspace plugin.

Answer: D


NEW QUESTION # 21
Which of the following are true regarding how the My Project Space (Project Workspace) handles dynamic content? (Choose two.)

  • A. If the project state is On Hold, actual start date and actual end date are displayed.
  • B. If the project state is Work in Progress, actual start date and planned end date are displayed.
  • C. If the project state is Pending or Open, planned start date and planned end date are displayed.
  • D. If the project state is Draft, actual start date and actual end date are displayed.

Answer: B,C


NEW QUESTION # 22
Which 'Member Preference' automatically finds the most available resource(s) from the group and allocates to a plan using the allocation action?

  • A. Specific member.
  • B. All members.
  • C. Any member.
  • D. Any member and specific member.

Answer: C


NEW QUESTION # 23
An it_project_manager can request resources by which of the following: (Choose two.)

  • A. Hours.
  • B. Day.
  • C. Month.
  • D. Person Days.

Answer: A,D


NEW QUESTION # 24
Where do you define 'Roles' requested via resource plans?

  • A. Resource roles under resource management.
  • B. Under skill management modules
  • C. No need to define it differently, they are same are system roles
  • D. Roles under system security

Answer: A


NEW QUESTION # 25
How does a project manager request a change to a resource plan in the requested state?

  • A. Email resource user.
  • B. Email resource manager
  • C. Request change on resource plan
  • D. Use notes on resource plan.

Answer: C


NEW QUESTION # 26
Which of the following roles can access the project administration application?

  • A. it_pps_admin.
  • B. it_project_manager.
  • C. it_project_user.
  • D. timecard_admin.

Answer: A


NEW QUESTION # 27
Demand managers can enhance a demand request by adding the following: (Choose three.)

  • A. Change Requests
  • B. Problems
  • C. Requirements
  • D. Stakeholders
  • E. Decisions

Answer: C,D,E


NEW QUESTION # 28
In what way would you restrict the assigned to field on a project task to only allow users with resource allocations to be assigned?

  • A. Create a reference qualifier on the 'assigned to' field.
  • B. Create an Access Control List (ACL) rule.
  • C. On the project record under the preferences tab select the "Derive assignee list from resource plan" preference.
  • D. The system automatically does this and can only be disabled by an admin.

Answer: C


NEW QUESTION # 29
Which of the following checks to see if the assessable record exists for the demand and creates an assessable record if none exists?

  • A. Update Demand State
  • B. Create OnDemand Assessment
  • C. Validate Assessment Metrics for Demand
  • D. Auto Business Rule for Assessments

Answer: B


NEW QUESTION # 30
Which capability allows users to view variances in a project's schedule?

  • A. Compare scheduled baselines
  • B. Project Status Report
  • C. Move project
  • D. Machine-learning algorithms

Answer: A


NEW QUESTION # 31
In the base system, what is the default number of cards that can be displayed in the project workspace?

  • A. 0
  • B. 1
  • C. 2
  • D. 3

Answer: C