CIS-PPM PDF Dumps May 05, 2023 Recently Updated Questions [Q32-Q56]

Share

CIS-PPM PDF Dumps | May 05, 2023 Recently Updated Questions

CIS-PPM Exam Questions – Valid CIS-PPM Dumps Pdf


Difficulty in Writing Certified Implementation Specialist - Project Portfolio Management (CIS PPM) Exam

Every exam can become a difficult one if not well prepared. Lots of study material for this exam is available online, at the official website, and in the form of CIS PPM exam dumps. If students practice these exam dumps and take the CIS PPM practice exams, they can surely overcome the exam difficulty and clear the exam with good grades. Below is a list of topics that students usually find difficult and challenging. Make sure you cover them in detail.

If you have a clear understanding of the following fields, you will have a decent probability of passing CIS PPM:

  • PPM positions, tables, fields, and properties, including project management, demand management, resource management & management of timesheets
  • Concepts and terms for Project Management
  • Lifecycle from definition to demand to project
  • Workspaces, dashboards, UIs, e.g. Demand workbench, visualization of timelines, investment platform, workbench for tools, planning console, PMO Dashboard
  • Fresh multicurrency plugin in Orlando, e.g.
  • Advanced setup, e.g. team spaces and separation of domains

 

NEW QUESTION 32
What role can configure an idea module, map idea categories to the idea module, and add navigation for the Idea Portal?

  • A. Idea admin [idea_admin]
  • B. Project manager [it_project_manager]
  • C. Idea manager [idea_manager]
  • D. Demand manager [it_demand_manager]

Answer: A

 

NEW QUESTION 33
Plugins may be added to the base platform in one of the following ways: (Choose three.)

  • A. Activated by an admin (not by default).
  • B. Activated by default in the base ServiceNow system.
  • C. Activated by an it_portfolio_manager.
  • D. Activated by an it_pps_admin.
  • E. Requested from ServiceNow.

Answer: A,B,E

 

NEW QUESTION 34
A project expense line is a cost associated with a specific source. Examples of specific sources could include:
(Choose three.)

  • A. Project.
  • B. Demand.
  • C. User.
  • D. Fixed Asset.
  • E. Configuration Item (CI).

Answer: C,D,E

 

NEW QUESTION 35
The RIDAC workflow can be modified by using which feature?

  • A. Service Catalog
  • B. Project Form
  • C. Idea Portal
  • D. Flow Designer

Answer: B

 

NEW QUESTION 36
In order for a business unit to have its own Idea Portal to retrieve data, what must be configured first?

  • A. Idea module
  • B. A business unit cannot have its own its own Idea Portal
  • C. Idea categories
  • D. Idea Portal URL

Answer: A

 

NEW QUESTION 37
Where are CAPEX and OPEX targets set for each fiscal year?

  • A. Cost Plans
  • B. Portfolio Target
  • C. Demand Workbench
  • D. Program Workbench

Answer: B

 

NEW QUESTION 38
What needs to be configured if a customer wants to change the attributes copied when using copy project or copy partial project?

  • A. com.snc.project.copy.
  • B. The copy project UI action
  • C. The copy project client script.
  • D. com.snc.project.copy.additional_attributes.

Answer: D

 

NEW QUESTION 39
In the base system, what is the default number of cards that can be displayed in the project workspace?

  • A. 0
  • B. 1
  • C. 2
  • D. 3

Answer: A

 

NEW QUESTION 40
What is the demand workbench used for? (Choose two.)

  • A. Comparing and prioritizing demands against other demands.
  • B. Comparing demands with portfolios.
  • C. Approving demands.
  • D. Displaying submitted demands to stakeholders.

Answer: A,D

 

NEW QUESTION 41
In which table can you find cost information for a specific fiscal period?

  • A. expense_line
  • B. cost_plan
  • C. cost_plan_breakdown
  • D. pm_project

Answer: C

 

NEW QUESTION 42
Demand managers can enhance a demand request by adding the following: (Choose three.)

  • A. Change Requests
  • B. Requirements
  • C. Problems
  • D. Stakeholders
  • E. Decisions

Answer: B,D,E

 

NEW QUESTION 43
Which of the following are true regarding how the My Project Space (Project Workspace) handles dynamic content? (Choose two.)

  • A. If the project state is On Hold, actual start date and actual end date are displayed.
  • B. If the project state is Draft, actual start date and actual end date are displayed.
  • C. If the project state is Work in Progress, actual start date and planned end date are displayed.
  • D. If the project state is Pending or Open, planned start date and planned end date are displayed.

Answer: C,D

 

NEW QUESTION 44
Which role can configure the parameters of the demand workbench that is provided with the base system?

  • A. it_pps_admin.
  • B. All roles.
  • C. it_project_manager
  • D. business_stakeholder.

Answer: A

 

NEW QUESTION 45
Where do you define 'Roles' requested via resource plans?

  • A. Roles under system security
  • B. No need to define it differently, they are same are system roles
  • C. Resource roles under resource management.
  • D. Under skill management modules

Answer: C

 

NEW QUESTION 46
The PPM Standard plugin enables an it_project_manager to perform the following activities: (Choose three.)

  • A. Track actual amount spent compared to an approved budget.
  • B. Establish resource requirements and track costs.
  • C. Determine overall project cost requirements
  • D. Configure cost type definition
  • E. Define target for the portfolio

Answer: A,B,C

 

NEW QUESTION 47
Where can a user export project data in either a MPP, XML or CSV format?

  • A. Related lists
  • B. Project Workbench
  • C. Planning Console
  • D. Demand Form

Answer: C

 

NEW QUESTION 48
A pps_admin role can configure the parameters that are displayed on a project card. The parameters displayed on a project card are derived from the records in what table?

  • A. CMDB Health Scorecard [cmdb_health_scorecard_group].
  • B. Project Time Card Exception [project_time_category].
  • C. PM Home Page Card [pm_home_page_card].
  • D. Theme [scrum_theme].

Answer: C

 

NEW QUESTION 49
What is the default schedule for a project?

  • A. 9-hour workday (from 8 to 12 and from 1 to 5).
  • B. 8-hour workday (from 8 to 12 and 1 to 5).
  • C. 8-hour workday (from 9 to 5).
  • D. 8-hour workday (from 9 to 12 and 1 to 6).

Answer: B

 

NEW QUESTION 50
When a time card is approved, the actual time is stored in which two tables? (Choose two.)

  • A. Resource Aggregate tables (Daily, Weekly, and Monthly)
  • B. Resource Allocation Daily table
  • C. Project Time table
  • D. Resource Event table

Answer: A,B

 

NEW QUESTION 51
When entering time worked into a time sheet, which feature is recommended to group different types of work (e.g., standard hours and overtime)?

  • A. Bill rate
  • B. Category
  • C. Rate model
  • D. Rate type

Answer: D

 

NEW QUESTION 52
In what way would you restrict the assigned to field on a project task to only allow users with resource allocations to be assigned?

  • A. Create a reference qualifier on the 'assigned to' field.
  • B. On the project record under the preferences tab select the "Derive assignee list from resource plan" preference.
  • C. The system automatically does this and can only be disabled by an admin.
  • D. Create an Access Control List (ACL) rule.

Answer: B

 

NEW QUESTION 53
Which roles can view reports on resource utilization and availability? (Choose two.)

  • A. resource_manager
  • B. pps_resource
  • C. resource_user
  • D. it_project_portfolio_user

Answer: A,C

 

NEW QUESTION 54
Which of the following roles can access the project administration application?

  • A. it_pps_admin.
  • B. timecard_admin.
  • C. it_project_manager.
  • D. it_project_user.

Answer: A

 

NEW QUESTION 55
When setting-up a program, planned ROI% is calculated based on: (Choose two.)

  • A. Values in the NPV field.
  • B. Values in the Planned cost field.
  • C. Values in the Planned return field.
  • D. Values in the Budgeted cost field.

Answer: B,C

 

NEW QUESTION 56
......

CIS-PPM dumps Sure Practice with 62 Questions: https://actualtests.passsureexam.com/CIS-PPM-pass4sure-exam-dumps.html